The 5th Call of the NAMA Facility was launched on 13 November 2017 and is now closed.
Deadline for electronic submission of NAMA Support Project (NSP) Outlines: 15 March 2018, 3 pm (CEST/GMT+2).
Indicative timeline of the project cycle under the 5th Call:
5th Call for NSP Outlines: | 13 November 2017 – 15 March 2018 |
Desk-based assessment of NSP Outlines: | 16 March – mid-May 2018 |
Decision on a shortlist of NSPs for onsite assessments and information of all applicants: | until 18 May 2018 |
Onsite assessments of shortlisted NSPs: | 28 May – 29 June |
NAMA Facility Board's decision on DPP funding for NSPs: | July – August 2018 |
Contracting of Detailed Preparation Phase (DPP): | late summer 2018 |
Detailed Preparation Phase (DPP): | up to 18 months |
Submission of NSP Proposals: | up to 18 months |
Funding decision based on NSP Proposals: | after submission of NSP Proposal |
Please note that all relevant 5th Call documents including a revised template for NAMA Support Project Outlines are available here.